Module 3 - Build a Prototype or Pilot for the Network Structure
Section 1 - Build the Prototype or Pilot
PH Network Services Corporation: Solution
The general manager of PH wants to make sure that the system can be installed
in a manner that will allow all offices to "come on line" in a phased-in
approach. Describe your method of installing the system.
-
The critical path on the implementation of the PH Network system will be
obtaining circuits from the local provider.
-
The Frame Relay circuits should be ordered as soon as possible.
-
A structured plan should be established for doctor offices to place orders
for ISDN lines as a coordinated order for the entire network.
-
One hospital, one doctor office with an existing LAN, and one single-PC
doctor office should be selected as a Phase I Group. The communication
lines for these offices and the PH Network office should be installed first.
-
The Catalyst 1900 switch and Cisco 3620 router should be installed in the
PH Network office. Access to the Windows NT server by local PCs should
be verified.
-
The pilot network of one hospital, one LAN-based doctor office, and one
standalone-based office should then be connected and completely tested
by ping tests and user logins.
-
The new SQL Server could then be added and the connection tested for the
pilot network. Once these tests have proven the operational status of the
network, the other hospitals should be added, followed by doctor offices,
with an orderly, planned methodology.